  • brock environmental center february 6th 2014

    (1 of 6)

  • brock environmental center february 14th 2014

    (2 of 6)

  • brock environmental center february 17th 2014

    (3 of 6)

  • brock environmental center february 21st 2014

    (4 of 6)

  • brock environmental center february 24th 2014

    (5 of 6)

  • brock environmental center february 28th 2014

    (6 of 6)

Previous
Next

February Construction Progress Photos

Through the end of February, there has been a significant amount of construction progress on the Brock Environmental Center. The following milestones have been completed:

– The balance of the concrete foundations to support the exterior wood walkway and deck
– Structural steel columns and beams to support the deck
– Acoustical roof decking that will support the roofing
– Primary exterior wood stud framing for the North side of the main building

Ninety percent of the site utilities are finished, including the installation of the primary leachate and grey water tanks. The balance of the structural steel for the multipurpose room and education pavilion has been delivered to the project for installation.