June Construction Update Photos

The Brock Environmental Center’s structural frame is complete and the building is dried in with the exception of windows. The triple glazed window systems will arrive in late June and be installed within 2 weeks in order to complete the dry in process.  All site utilities including storm water, sewer, water and power have been completed, as well as mechanical and electrical rough-ins.